The Orange County Housing Finance Trust, County, and Cities share a common goal of creating 2,700 permanent supportive housing units by June 30, 2025. This page tracks the progress of that goal since June 2018 and reports the details related to each project.
Click on each push pin to obtain detailed project information. Zoom in and out to see overlapping push pins. Click on the link below the map to view a full screen version of the map.
Service Planning Area | Total PSH | % PSH | Total Units | % Total Units |
Central | 654 | 50% | 1,188 | 45% |
North | 542 | 42% | 1,045 | 40% |
South | 110 | 8% | 401 | 15% |
Grand Total | 1,306 | 100% | 2,634 | 100% |
Project Status | PSH-Units | % PSH | Total Units | % Total Units |
Complete | 479 | 37% | 1,004 | 38% |
In progress of funding | 219 | 17% | 520 | 20% |
Under Construction | 608 | 47% | 1,110 | 42% |
Grand Total | 1,306 | 100% | 2,634 | 100% |
Updated November 29, 2022 |
In addition, the Orange County Housing Finance Trust maintains a development pipeline to help anticipate future project needs and advocate for more resources for affordable housing in Orange County. Projects that are on the Trust’s pipeline receive points in the annual NOFAs. Developers can add their projects to the Trust’s pipeline here.
Past Funded Projects
On May 17, 2023 the Board approved funding the following affordable and permanent supportive housing developments. | |||||||||||
2023 | |||||||||||
Project Name | Address | SPA | Developer | Project Status | Trust Funded Units1 |
Total Project Units |
County General Fund |
State General Funds |
MHSA Funds |
LHTF Funds |
Total Funding |
Costa Mesa Motel 6 Phase 2 | 2274 Newport Boulevard Costa Mesa, CA 92627 |
Central | Community Development Partners |
Expected construction start 2024 |
28 | 85 | $1,177,731.03 | $0 | $368,460.00 | $0 | $1,546,191.03 |
St. Anselm's Apartments | 9710 Belfast Drive Garden Grove, CA 92844 |
Central | Domus Development | Expected construction start 2024 |
31 | 105 | $0 | $0 | $2,579,220.00 | $0 | $2,579,220.00 |
Milton Manor | 13800, 13802 & 13812 Milton Avenue Westminster, CA 92683 |
Central | Retirement Housing Foundation |
Expected construction start 2024 |
6 | 54 | $384,615.38 | $0 | $0 | $365,384.62 | $750,000.00 |
North Harbor Village | 1108 N. Harbor Blvd Santa Ana, CA 92703 |
Central | Jamboree Housing Corporation |
Under Construction | 7 | 91 | $0 | $0 | $1,289,610.00 | $0 | $1,289,610.00 |
Marks Way | 164 S. Marks Way Orange, CA 92868 |
North | National CORE |
Expected construction start 2025 |
13 | 51 | $0 | $0 | $2,394,990.00 | $0 | $2,394,990.00 |
The Orion | 1800 E La Veta Orange, CA 92866 |
North | USA Properties | Expected construction start 2024 |
3 | 166 | $0 | $0 | $503,501.60 | $0 | $503,501.60 |
Capitol Funding Total | 88 | 552 | $1,562,346.41 | $0 | $7,135,781.60 | $365,384.62 | $9,063,512.63 | ||||
LHTF Administrative Funding Total | $19,230.77 | ||||||||||
LHTF Grand Total | $384,615.39 | ||||||||||
NOTES: 1. All Trust funded units are restricted to 30% of Area Median Income regardless of funding source. |
|||||||||||
On May 18, 2022 the Board approved funding the following affordable and permanent supportive housing developments. | |||||||||||
2022 | |||||||||||
Project Name | Address | SPA | Developer | Project Status | Trust Funded Units1 |
Total Project Units |
County General Fund |
State General Funds |
MHSA Funds2 |
LHTF Funds |
Total Funding |
Costa Mesa Motel 6 Phase 2 | 2274 Newport Boulevard Costa Mesa, CA 92627 |
Central | Community Development Partners |
Expected construction start 2024 |
2 | 88 | $200,000.00 | $0 | $0 | $0 | $200,000.00 |
Lincoln Ave. Apartments | 7101 Lincoln Avenue Buena Park, CA 90620 |
North | C&C Development | Expected construction start 2024 |
10 | 55 | $237,653.59 | $0 | $354,290.00 | $562,346.41 | $1,154,290.00 |
WISEPlace | 1411 N. Broadway Avenue Santa Ana, CA 92706 |
Central | Jamboree Housing Corporation |
Under Construction | 14 | 48 | $0 | $0 | $2,480,030.00 | $0 | $2,480,030.00 |
Capitol Funding Total | 26 | 191 | $437,653.59 | $0 | $2,834,320.00 | $562,346.41 | $3,834,320.00 | ||||
LHTF Administrative Funding Total | $29,597.18 | ||||||||||
LHTF Grand Total | $591,943.59 | ||||||||||
NOTES: 1. All Trust funded units are restricted to 30% of Area Median Income regardless of funding source. 2. The LHTF funds awarded to these projects will come from the Trust's 2023 LHTF Progarm award, as the Trust was not awarded LHTF funds for these projects in 2022. |
|||||||||||
On May 19, 2021 the Board approved funding the following affordable and permanent supportive housing developments. | |||||||||||
2021 | |||||||||||
Project Name | City | SPA | Developer | Project Status | Trust Funded Units |
Total Project Units |
County General Fund |
State General Funds |
MHSA Funds |
LHTF Funds |
Total Funding |
Paseo Adelanto | San Juan Capistrano | South | Jamboree Housing Corporation |
Under construction | 26 | 50 | $0 | $0 | $1,703,314.50 | $1,600,000.00 | $3,303,314.50 |
Westview House | Santa Ana | Central | Community Development Partners |
Under construction | 25 | 85 | $791,139.00 | $0 | $0 | $659,210.19 | $1,450,349.19 |
Valencia Garden (formerly Orange Corporate Yard) |
Orange | North | C&C Development | Under construction | 6 | 62 | $208,861.00 | $0 | $0 | $175,233.09 | $384,094.09 |
Miraflores (formerly Anaheim Midway) |
Anaheim | North | National CORE | Under construction | 8 | 86 | $0 | $0 | $738,455.08 | $624,196.92 | $1,362,652.00 |
Crossroads at Washington | Santa Ana | Central | The Related Companies |
Under construction | 20 | 86 | $0 | $0 | $1,354,812.29 | $1,145,187.71 | $2,500,000.00 |
Meadows Senior Apartments | Lake Forest | South | C&C Development | Under construction | 7 | 65 | $0 | $0 | $646,147.91 | $546,172.09 | $1,192,320.00 |
Capitol Funding Total | 92 | 434 | $1,000,000.00 | $0 | $4,442,729.78 | $4,750,000.00 | $10,192,729.78 | ||||
LHTF Administrative Funding Total | $250,000.00 | ||||||||||
LHTF Grand Total | $5,000,000.00 | ||||||||||
On May 6, 2020 the Board approved funding the following affordable and permanent supportive housing developments. | |||||||||||
2020 | |||||||||||
Project Name | City | SPA | Developer | Project Status | Trust Funded Units |
Total Project Units |
County General Fund |
State General Funds |
MHSA Funds |
LHTF Funds |
Total Funding |
Ascent (formerly Airport Inn) |
Buena Park | North | Jamboree Housing Corporation |
Completed | 16 | 58 | $407,692.31 | $387,307.69 | $0 | $407,692.31 | $1,202,692.31 |
Center of Hope Phase 1 | Anaheim | North | Salvation Army | Completed | 16 | 72 | $0 | $0 | $1,250,000.00 | $1,168,062.05 | $2,418,062.05 |
Orchard View Senior Gardens | Buena Park | North | National CORE | Under construction | 5 | 66 | $0 | $0 | $409,450.00 | $382,610.41 | $792,060.41 |
Santa Angelina Senior Community | Placentia | North | National CORE | Under construction | 5 | 65 | $0 | $0 | $409,450.00 | $382,610.41 | $792,060.41 |
North Harbor Village | Santa Ana | Central | Jamboree Housing Corporation |
Under construction | 14 | 91 | $0 | $0 | $1,146,460.00 | $1,071,309.14 | $2,217,769.14 |
FX Residences | Santa Ana | Central | HomeAid OC | Under construction | 16 | 17 | $282,051.28 | $267,948.72 | $0 | $282,051.28 | $832,051.28 |
Mountain View | Lake Forest | South | National CORE | Completed | 11 | 71 | $310,256.41 | $294,743.59 | $0 | $310,256.41 | $915,256.41 |
Capitol Funding Total | 83 | 440 | $1,000,000.00 | $950,000.00 | $3,215,360.00 | $4,004,592.01 | $9,169,952.01 | ||||
LHTF Administrative Funding Total | $210,768.00 | ||||||||||
LHTF Grand Total | $4,215,360.01 |
Last updated June 23, 2023.