The Orange County Housing Finance Trust, County, and Cities share a common goal of creating 2,700 permanent supportive housing units by June 30, 2025. This page tracks the progress of that goal since June 2018 and reports the details related to each project.

Click on each push pin to obtain detailed project information. Zoom in and out to see overlapping push pins. Click on the link below the map to view a full screen version of the map.

Service Planning Area Total PSH % PSH Total Units % Total Units
Central 804 54% 1,741 51%
North 567 38% 1,302 38%
South 110 7% 401 12%
Grand Total 1,481 100% 3,444 100%

Project Status PSH-Units % PSH Total Units % Total Units
In Progress of Funding 180 12% 748 22%
Under Construction 443 30% 1,068 31%
Completed 858 58% 1,628 47%
Grand Total 1,481 100% 3,444 100%

Updated August 26, 2024
 
 
 

In addition, the Orange County Housing Finance Trust maintains a development pipeline to help anticipate future project needs and advocate for more resources for affordable housing in Orange County. Projects that are on the Trust’s pipeline receive points in the annual NOFAs. Developers can add their projects to the Trust’s pipeline here.

 

Past Funded Projects

2024
On May 15, 2024 and September 18, 2024, the Board approved funding the following affordable and permanent supportive housing developments.
Project Name Address SPA Developer Project Status Trust
Funded
Units1
Total
Project
Units
County
General
Fund
MHSA
Funds
LHTF
Funds
Total
Funding
Altrudy II Senior Apartments 18597 and 18602 Altrudy Lane
Yorba Linda, CA 92886
North C&C Development Expected construction
start 2025
13 72 $0 $1,159,425.65 $1,101,374.352 $2,260,800.00
Milton Manor 13800, 13802 & 13812 Milton Avenue
Westminster, CA 92683
Central Retirement
Housing
Foundation
Expected construction
start 2025
14 54 $1,000,000.00 $0 $950,000.003 $1,950,000.00
Goldenwest Apartments4 14125 Goldenwest Street
Westminster, CA 92683
Central American
Family
Housing
Expected construction
start 2025
21 29 $0 $1,724,400.00 $1,638,180.00 $3,362,580.00
Metro on Melrose4 211 W Crowther Avenue
Placentia, CA 92870
North USA Properties
Fund, Inc
Expected construction
start 2025
18 189 $0 $1,532,800.00 $1,456,160.00 $2,988,960.00
Costa Mesa Senior4 695 W. 19th St.
Costa Mesa, CA 92627
Central Jamboree
Housing
Corporation
Expected construction
start 2025
21 59 $0 $1,844,340.00 $1,655,660.00 $3,500,000.00
Cypress Village Sand Canyon and Great Park Blvd
Irvine, CA 92618
South Irvine
Community
Land Trust
Expected construction
start 2025
21 200 $0 $1,794,871.80 $1,705,128.202 $3,500,000.00
MTF HB 21845 Magnolia Street
Huntington Beach, CA 92646
Central National CORE Expected construction
start 2025
8 51 $0 $1,532,800.00 $0 $1,532,800.00
Aspan Court 22471 Aspan Street
Lake Forest, CA 92630
South National COREt Expected construction
start 2025
19 60 $0 $1,789,743.593 $1,700,256.41 $3,490,000.00
Capitol Funding Total 135 714 $1,000,000.00 $11,378,381.04 $10,206,758.97 $22,585,140.00
LHTF Administrative Funding Total $537,197.845
LHTF Grand Total $10,743,956.81
NOTES:
1. All Trust funded units are restricted to 30% of Area Median Income regardless of funding source.
2. Alturdy II and Cypress Village were awarded LHTF funding from the Trust's 2022 LHTF award.
3. Milton Manor and Aspan Court were awarded LHTF funding from the Trust's 2023 LHTF award.
4. Projects in bold were awarded LHTF funding contingent on the Trust receiving a LHTF award for 2024.
5. The LHTF administrative funding includes $152,434.01 from the 2022 LHTF award, $139,487.18 from the 2023 LHTF award, and $250,000 from the anticipated 2024 LHTF award.
2023
On May 17, 2023 and December 12, 2023, the Board approved funding the following affordable and permanent supportive housing developments.
Project Name Address SPA Developer Project Status Trust
Funded
Units1
Total
Project
Units
County
General
Fund
Federal
General
Funds
MHSA
Funds
LHTF
Funds
Total
Funding
Costa Mesa Motel 6 Phase 2 2274 Newport Boulevard
Costa Mesa, CA 92627
Central Community
Development
Partners
Expected construction
start 2024
28 85 $1,177,731.03 $0 $368,460.00 $0 $1,546,191.03
St. Anselm's Apartments 9710 Belfast Drive
Garden Grove, CA 92844
Central Domus Development Expected construction
start 2024
31 105 $0 $0 $2,579,220.00 $0 $2,579,220.00
Milton Manor 13800, 13802 & 13812 Milton Avenue
Westminster, CA 92683
Central Retirement
Housing
Foundation
Expected construction
start 2025
6 54 $384,615.38 $0 $0 $365,384.62 $750,000.00
North Harbor Village 1108 N. Harbor Blvd
Santa Ana, CA 92703
Central Jamboree
Housing
Corporation
Under Construction 7 91 $0 $0 $1,289,610.00 $0 $1,289,610.00
Marks Way 164 S. Marks Way
Orange, CA 92868
North National
CORE
Expected construction
start 2025
13 51 $0 $2,850,000.00 $544,990.00 $0 $3,394,990.00
The Orion 1800 E La Veta
Orange, CA 92866
North USA Properties Under Construction 3 166 $0 $0 $503,501.60 $0 $503,501.60
Capitol Funding Total 88 552 $1,562,346.41 $2,850,000.00 $5,285,781.60 $365,384.62 $10,063,512.63
LHTF Administrative Funding Total $19,230.77
LHTF Grand Total $384,615.39
NOTES:
1. All Trust funded units are restricted to 30% of Area Median Income regardless of funding source.
2022
On May 18, 2022 the Board approved funding the following affordable and permanent supportive housing developments.
Project Name Address SPA Developer Project Status Trust
Funded
Units1
Total
Project
Units
County
General
Fund
State
General
Funds
MHSA
Funds2
LHTF
Funds
Total
Funding
Costa Mesa Motel 6 Phase 2 2274 Newport Boulevard
Costa Mesa, CA 92627
Central Community
Development
Partners
Expected construction
start 2024
2 88 $200,000.00 $0 $0 $0 $200,000.00
Lincoln Ave. Apartments 7101 Lincoln Avenue
Buena Park, CA 90620
North C&C Development Expected construction
start 2024
10 55 $237,653.59 $0 $354,290.00 $562,346.41 $1,154,290.00
WISEPlace 1411 N. Broadway Avenue
Santa Ana, CA 92706
Central Jamboree
Housing
Corporation
Under Construction 14 48 $0 $0 $2,480,030.00 $0 $2,480,030.00
Capitol Funding Total 26 191 $437,653.59 $0 $2,834,320.00 $562,346.41 $3,834,320.00
LHTF Administrative Funding Total $29,597.18
LHTF Grand Total $591,943.59
NOTES:
1. All Trust funded units are restricted to 30% of Area Median Income regardless of funding source.
2. The LHTF funds awarded to these projects will come from the Trust's 2023 LHTF Progarm award, as the Trust was not awarded LHTF funds for these projects in 2022.
2021
On May 19, 2021 the Board approved funding the following affordable and permanent supportive housing developments.
Project Name City SPA Developer Project Status Trust
Funded
Units
Total
Project
Units
County
General
Fund
State
General
Funds
MHSA
Funds
LHTF
Funds
Total
Funding
Paseo Adelanto San Juan Capistrano South Jamboree
Housing
Corporation
Under construction 26 50 $0 $0 $1,703,314.50 $1,600,000.00 $3,303,314.50
Westview House Santa Ana Central Community
Development
Partners
Under construction 25 85 $791,139.00 $0 $0 $659,210.19 $1,450,349.19
Valencia Garden
(formerly Orange Corporate Yard)
Orange North C&C Development Completed 6 62 $208,861.00 $0 $0 $175,233.09 $384,094.09
Miraflores
(formerly Anaheim Midway)
Anaheim North National CORE Under construction 8 86 $0 $0 $738,455.08 $624,196.92 $1,362,652.00
Crossroads at Washington Santa Ana Central The Related
Companies
Completed 20 86 $0 $0 $1,354,812.29 $1,145,187.71 $2,500,000.00
Meadows Senior Apartments Lake Forest South C&C Development Under construction 7 65 $0 $0 $646,147.91 $546,172.09 $1,192,320.00
Capitol Funding Total 92 434 $1,000,000.00 $0 $4,442,729.78 $4,750,000.00 $10,192,729.78
LHTF Administrative Funding Total $250,000.00
LHTF Grand Total $5,000,000.00
2020
On May 6, 2020 the Board approved funding the following affordable and permanent supportive housing developments.
Project Name City SPA Developer Project Status Trust
Funded
Units
Total
Project
Units
County
General
Fund
State
General
Funds
MHSA
Funds
LHTF
Funds
Total
Funding
Ascent
(formerly Airport Inn)
Buena Park North Jamboree
Housing
Corporation
Completed 16 58 $407,692.31 $387,307.69 $0 $407,692.31 $1,202,692.31
Center of Hope Phase 1 Anaheim North Salvation Army Completed 16 72 $0 $0 $1,250,000.00 $1,168,062.05 $2,418,062.05
Orchard View Senior Gardens Buena Park North National CORE Under construction 5 66 $0 $0 $409,450.00 $382,610.41 $792,060.41
Santa Angelina Senior Community Placentia North National CORE Completed 5 65 $0 $0 $409,450.00 $382,610.41 $792,060.41
North Harbor Village Santa Ana Central Jamboree
Housing
Corporation
Under construction 14 91 $0 $0 $1,146,460.00 $1,071,309.14 $2,217,769.14
FX Residences Santa Ana Central HomeAid OC Under construction 16 17 $282,051.28 $267,948.72 $0 $282,051.28 $832,051.28
Mountain View Lake Forest South National CORE Completed 11 71 $310,256.41 $294,743.59 $0 $310,256.41 $915,256.41
Capitol Funding Total 83 440 $1,000,000.00 $950,000.00 $3,215,360.00 $4,004,592.01 $9,169,952.01
LHTF Administrative Funding Total $210,768.00
LHTF Grand Total $4,215,360.01
 

Last updated October 28, 2024.