Developments
The Orange County Housing Finance Trust, County, and Cities share a common goal of creating 2,700 permanent supportive housing units by June 30, 2025. This page tracks the progress of that goal since June 2018 and reports the details related to each project.
Click on each push pin to obtain detailed project information. Zoom in and out to see overlapping push pins. Click on the link below the map to view a full screen version of the map.
Service Planning Area | Total PSH | % PSH | Total Units | % Total Units |
Central | 804 | 54% | 1,741 | 51% |
North | 567 | 38% | 1,302 | 38% |
South | 110 | 7% | 401 | 12% |
Grand Total | 1,481 | 100% | 3,444 | 100% |
Project Status | PSH-Units | % PSH | Total Units | % Total Units |
In Progress of Funding | 180 | 12% | 748 | 22% |
Under Construction | 443 | 30% | 1,068 | 31% |
Completed | 858 | 58% | 1,628 | 47% |
Grand Total | 1,481 | 100% | 3,444 | 100% |
Updated August 26, 2024 |
In addition, the Orange County Housing Finance Trust maintains a development pipeline to help anticipate future project needs and advocate for more resources for affordable housing in Orange County. Projects that are on the Trust’s pipeline receive points in the annual NOFAs. Developers can add their projects to the Trust’s pipeline here.
Past Funded Projects
2024 | |||||||||||
On May 15, 2024 and September 18, 2024, the Board approved funding the following affordable and permanent supportive housing developments. | |||||||||||
Project Name | Address | SPA | Developer | Project Status | Trust Funded Units1 |
Total Project Units |
County General Fund |
MHSA Funds |
LHTF Funds |
Total Funding |
|
Altrudy II Senior Apartments | 18597 and 18602 Altrudy Lane Yorba Linda, CA 92886 |
North | C&C Development | Expected construction start 2025 |
13 | 72 | $0 | $1,159,425.65 | $1,101,374.352 | $2,260,800.00 | |
Milton Manor | 13800, 13802 & 13812 Milton Avenue Westminster, CA 92683 |
Central | Retirement Housing Foundation |
Expected construction start 2025 |
14 | 54 | $1,000,000.00 | $0 | $950,000.003 | $1,950,000.00 | |
Goldenwest Apartments4 | 14125 Goldenwest Street Westminster, CA 92683 |
Central | American Family Housing |
Expected construction start 2025 |
21 | 29 | $0 | $1,724,400.00 | $1,638,180.00 | $3,362,580.00 | |
Metro on Melrose4 | 211 W Crowther Avenue Placentia, CA 92870 |
North | USA Properties Fund, Inc |
Expected construction start 2025 |
18 | 189 | $0 | $1,532,800.00 | $1,456,160.00 | $2,988,960.00 | |
Costa Mesa Senior4 | 695 W. 19th St. Costa Mesa, CA 92627 |
Central | Jamboree Housing Corporation |
Expected construction start 2025 |
21 | 59 | $0 | $1,844,340.00 | $1,655,660.00 | $3,500,000.00 | |
Cypress Village | Sand Canyon and Great Park Blvd Irvine, CA 92618 |
South | Irvine Community Land Trust |
Expected construction start 2025 |
21 | 200 | $0 | $1,794,871.80 | $1,705,128.202 | $3,500,000.00 | |
MTF HB | 21845 Magnolia Street Huntington Beach, CA 92646 |
Central | National CORE | Expected construction start 2025 |
8 | 51 | $0 | $1,532,800.00 | $0 | $1,532,800.00 | |
Aspan Court | 22471 Aspan Street Lake Forest, CA 92630 |
South | National COREt | Expected construction start 2025 |
19 | 60 | $0 | $1,789,743.593 | $1,700,256.41 | $3,490,000.00 | |
Capitol Funding Total | 135 | 714 | $1,000,000.00 | $11,378,381.04 | $10,206,758.97 | $22,585,140.00 | |||||
LHTF Administrative Funding Total | $537,197.845 | ||||||||||
LHTF Grand Total | $10,743,956.81 | ||||||||||
NOTES: 1. All Trust funded units are restricted to 30% of Area Median Income regardless of funding source. 2. Alturdy II and Cypress Village were awarded LHTF funding from the Trust's 2022 LHTF award. 3. Milton Manor and Aspan Court were awarded LHTF funding from the Trust's 2023 LHTF award. 4. Projects in bold were awarded LHTF funding contingent on the Trust receiving a LHTF award for 2024. 5. The LHTF administrative funding includes $152,434.01 from the 2022 LHTF award, $139,487.18 from the 2023 LHTF award, and $250,000 from the anticipated 2024 LHTF award. |
2023 | |||||||||||
On May 17, 2023 and December 12, 2023, the Board approved funding the following affordable and permanent supportive housing developments. | |||||||||||
Project Name | Address | SPA | Developer | Project Status | Trust Funded Units1 |
Total Project Units |
County General Fund |
Federal General Funds |
MHSA Funds |
LHTF Funds |
Total Funding |
Costa Mesa Motel 6 Phase 2 | 2274 Newport Boulevard Costa Mesa, CA 92627 |
Central | Community Development Partners |
Expected construction start 2024 |
28 | 85 | $1,177,731.03 | $0 | $368,460.00 | $0 | $1,546,191.03 |
St. Anselm's Apartments | 9710 Belfast Drive Garden Grove, CA 92844 |
Central | Domus Development | Expected construction start 2024 |
31 | 105 | $0 | $0 | $2,579,220.00 | $0 | $2,579,220.00 |
Milton Manor | 13800, 13802 & 13812 Milton Avenue Westminster, CA 92683 |
Central | Retirement Housing Foundation |
Expected construction start 2025 |
6 | 54 | $384,615.38 | $0 | $0 | $365,384.62 | $750,000.00 |
North Harbor Village | 1108 N. Harbor Blvd Santa Ana, CA 92703 |
Central | Jamboree Housing Corporation |
Under Construction | 7 | 91 | $0 | $0 | $1,289,610.00 | $0 | $1,289,610.00 |
Marks Way | 164 S. Marks Way Orange, CA 92868 |
North | National CORE |
Expected construction start 2025 |
13 | 51 | $0 | $2,850,000.00 | $544,990.00 | $0 | $3,394,990.00 |
The Orion | 1800 E La Veta Orange, CA 92866 |
North | USA Properties | Under Construction | 3 | 166 | $0 | $0 | $503,501.60 | $0 | $503,501.60 |
Capitol Funding Total | 88 | 552 | $1,562,346.41 | $2,850,000.00 | $5,285,781.60 | $365,384.62 | $10,063,512.63 | ||||
LHTF Administrative Funding Total | $19,230.77 | ||||||||||
LHTF Grand Total | $384,615.39 | ||||||||||
NOTES: 1. All Trust funded units are restricted to 30% of Area Median Income regardless of funding source. |
2022 | |||||||||||
On May 18, 2022 the Board approved funding the following affordable and permanent supportive housing developments. | |||||||||||
Project Name | Address | SPA | Developer | Project Status | Trust Funded Units1 |
Total Project Units |
County General Fund |
State General Funds |
MHSA Funds2 |
LHTF Funds |
Total Funding |
Costa Mesa Motel 6 Phase 2 | 2274 Newport Boulevard Costa Mesa, CA 92627 |
Central | Community Development Partners |
Expected construction start 2024 |
2 | 88 | $200,000.00 | $0 | $0 | $0 | $200,000.00 |
Lincoln Ave. Apartments | 7101 Lincoln Avenue Buena Park, CA 90620 |
North | C&C Development | Expected construction start 2024 |
10 | 55 | $237,653.59 | $0 | $354,290.00 | $562,346.41 | $1,154,290.00 |
WISEPlace | 1411 N. Broadway Avenue Santa Ana, CA 92706 |
Central | Jamboree Housing Corporation |
Under Construction | 14 | 48 | $0 | $0 | $2,480,030.00 | $0 | $2,480,030.00 |
Capitol Funding Total | 26 | 191 | $437,653.59 | $0 | $2,834,320.00 | $562,346.41 | $3,834,320.00 | ||||
LHTF Administrative Funding Total | $29,597.18 | ||||||||||
LHTF Grand Total | $591,943.59 | ||||||||||
NOTES: 1. All Trust funded units are restricted to 30% of Area Median Income regardless of funding source. 2. The LHTF funds awarded to these projects will come from the Trust's 2023 LHTF Progarm award, as the Trust was not awarded LHTF funds for these projects in 2022. |
2021 | |||||||||||
On May 19, 2021 the Board approved funding the following affordable and permanent supportive housing developments. | |||||||||||
Project Name | City | SPA | Developer | Project Status | Trust Funded Units |
Total Project Units |
County General Fund |
State General Funds |
MHSA Funds |
LHTF Funds |
Total Funding |
Paseo Adelanto | San Juan Capistrano | South | Jamboree Housing Corporation |
Under construction | 26 | 50 | $0 | $0 | $1,703,314.50 | $1,600,000.00 | $3,303,314.50 |
Westview House | Santa Ana | Central | Community Development Partners |
Under construction | 25 | 85 | $791,139.00 | $0 | $0 | $659,210.19 | $1,450,349.19 |
Valencia Garden (formerly Orange Corporate Yard) |
Orange | North | C&C Development | Completed | 6 | 62 | $208,861.00 | $0 | $0 | $175,233.09 | $384,094.09 |
Miraflores (formerly Anaheim Midway) |
Anaheim | North | National CORE | Under construction | 8 | 86 | $0 | $0 | $738,455.08 | $624,196.92 | $1,362,652.00 |
Crossroads at Washington | Santa Ana | Central | The Related Companies |
Completed | 20 | 86 | $0 | $0 | $1,354,812.29 | $1,145,187.71 | $2,500,000.00 |
Meadows Senior Apartments | Lake Forest | South | C&C Development | Under construction | 7 | 65 | $0 | $0 | $646,147.91 | $546,172.09 | $1,192,320.00 |
Capitol Funding Total | 92 | 434 | $1,000,000.00 | $0 | $4,442,729.78 | $4,750,000.00 | $10,192,729.78 | ||||
LHTF Administrative Funding Total | $250,000.00 | ||||||||||
LHTF Grand Total | $5,000,000.00 |
2020 | |||||||||||
On May 6, 2020 the Board approved funding the following affordable and permanent supportive housing developments. | |||||||||||
Project Name | City | SPA | Developer | Project Status | Trust Funded Units |
Total Project Units |
County General Fund |
State General Funds |
MHSA Funds |
LHTF Funds |
Total Funding |
Ascent (formerly Airport Inn) |
Buena Park | North | Jamboree Housing Corporation |
Completed | 16 | 58 | $407,692.31 | $387,307.69 | $0 | $407,692.31 | $1,202,692.31 |
Center of Hope Phase 1 | Anaheim | North | Salvation Army | Completed | 16 | 72 | $0 | $0 | $1,250,000.00 | $1,168,062.05 | $2,418,062.05 |
Orchard View Senior Gardens | Buena Park | North | National CORE | Under construction | 5 | 66 | $0 | $0 | $409,450.00 | $382,610.41 | $792,060.41 |
Santa Angelina Senior Community | Placentia | North | National CORE | Completed | 5 | 65 | $0 | $0 | $409,450.00 | $382,610.41 | $792,060.41 |
North Harbor Village | Santa Ana | Central | Jamboree Housing Corporation |
Under construction | 14 | 91 | $0 | $0 | $1,146,460.00 | $1,071,309.14 | $2,217,769.14 |
FX Residences | Santa Ana | Central | HomeAid OC | Under construction | 16 | 17 | $282,051.28 | $267,948.72 | $0 | $282,051.28 | $832,051.28 |
Mountain View | Lake Forest | South | National CORE | Completed | 11 | 71 | $310,256.41 | $294,743.59 | $0 | $310,256.41 | $915,256.41 |
Capitol Funding Total | 83 | 440 | $1,000,000.00 | $950,000.00 | $3,215,360.00 | $4,004,592.01 | $9,169,952.01 | ||||
LHTF Administrative Funding Total | $210,768.00 | ||||||||||
LHTF Grand Total | $4,215,360.01 |